1. Grant Road widening
Project: Harris County Precinct 3 will widen Grant Road from a two-lane roadway to a four-lane divided concrete boulevard in phases: from Spring Cypress Road to Shaw Road (Phase 2), from Shaw Road to Telge Road (Phase 3), and from Telge Road to Cypress Rosehill Road (Phase 4). Grant Road was widened from Lakewood Forest Drive to Louetta Road between 2017-2019.
Update: This project is in the study phase and is expected to start going out to bid in 2026.
2. North Eldridge Parkway widening
Project: Harris County Precinct 3 will widen North Eldridge Parkway to a four-lane divided concrete boulevard from south of Pine Drive to south of Lakewood Meadow Drive. The project is located near Cypress Park and the confluence of Cypress Creek and Little Cypress Creek.
Update: This project is in the design phase.
3. Cypress North Houston Road widening
Project: The two-lane roadway will be widened to a four-lane divided concrete boulevard from Jones Road to Perry Road.
Update: This project is in the design phase.
4. Greenhouse Road tunnel under Hwy. 290
Project: Officials will construct an underpass beneath Hwy. 290 from Mound Road to north of Hwy. 290, extending Greenhouse Road to Skinner Road.
Update: This project is in the design phase.
5. Greenhouse Road bridge over Cypress Creek
Project: Harris County Precinct 3 is completing a four-lane boulevard section south of Mound Road.
Update: This project is in the construction phase.